Following are expected traffic impacts from construction in the Inner Eastside for the coming weeks.
Broadway Bridge, FULL CLOSURE: Now thru September 3
Track construction is underway and the Broadway Bridge will be closed to ALL BRIDGE USERS (motor vehicles, bicycles, pedestrians) now through September 3. Detours are in place, and posted online at www.PortlandOnline.com/KeepPortlandMoving (Portland Streetcar Loop Project)
N Broadway St – Vancouver to Broadway Bridge, lane closures in both travel directions: Now thru September 3
Track infrastructure, utility, and paving work are underway. (Paving work is weather dependant.) Expect significant traffic congestion & delays. NOTE: This location will include NIGHT work. (Portland Streetcar Loop Project)
E Burnside St – 14th to 22nd, lane closures: August 23 – September 3
Old manhole abandonment work is taking place. One lane of traffic in each direction will be closed. Expect traffic congestions & delays. (Oak Basin Sewer Project)
E Burnside St – MLK to 14th, ONE-WAY eastbound: Permanently
This segment of Burnside was once Two-Way traffic, but has changed to ONE-WAY eastbound traffic permanently as part of the Burnside / Couch Couplet project’s street reconfiguration plan. NOTE: Although no travel lanes are impacted with 2 lanes maintained at all times, construction has now shifted from the north side of the street to the south side. Exercise caution when driving in the area of the work zone. (Burnside / Couch Couplet Project)
NE Davis St – MLK to Grand, CLOSED: Now thru August 27
Sewer work is underway, followed by paving work. (Paving work is weather dependant.) Expect traffic congestion & delays. (Portland Streetcar Loop Project)
NE Davis St – Grand to 6th, eastbound lane CLOSED: now thru September 3
Sewer work is underway. Eastbound travelers may use NE Everett to 6th; the Davis/6th intersection is open. (Burnside / Couch Couplet Project)
SE Elliott Ave – Hawthorne/20th to Hazel, CLOSED: Sunday, August 15, 8:00 AM – 6:00 PM
This street block is CLOSED for a community event to benefit the Hawthorne Boulevard Business Association. (Portland Bureau of Transportation)
SE Hawthorne Blvd – Grand to 12th, possible lane closures: Now thru August 27, 7:00 AM – 4:00 PM
Pavement rehabilitation work is complete and the contractor is adjusting utilities, signposts, etc. Traffic lanes should be open, but expect possible delays resulting from the construction zone. (SE Portland Pavement Preservation Project)
SE Hawthorne Blvd – 12th to 14th, possible lane closures: Now thru August 27, 9:00 AM – 3:00 PM
Pavement rehabilitation work is complete and the contractor is adjusting utilities, signposts, etc., to be followed by permanent pavement markings. Traffic lanes should be open, but expect possible delays resulting from the construction zone. (SE Portland Pavement Preservation Project)
NE Lloyd Blvd – Grand to 11th, eastbound lane closure: Now thru December 2011
One eastbound travel lane will be closed all hours for Portland Streetcar rail line staging and storage. (Portland Streetcar Loop Project)
SE Madison St – 12th to Grand, lane closures: Now thru August 27, 9:00 AM – 6:00 PM
Pavement rehabilitation work is underway. Traffic lanes should be open during daytime hours, but expect possible delays resulting from the construction zone. (SE Portland Pavement Preservation Project)
SE Oak St – at 10th, intersection closed: Now thru November 2010
The SE 10th and Oak Street Drop Shaft sewer crews are excavating the shaft. The intersection will be closed in all directions. Traffic will be detoured around the intersection. (Oak Basin Sewer Project)
NE Sandy Blvd – 12th to 14th, CLOSED: Permanently
This segment of Sandy is now CLOSED permanently as part of the Burnside / Couch Couplet project’s street reconfiguration plan. (Burnside / Couch Couplet Project)
NE Sandy Blvd – Westbound traffic DIVERTED to Couch at 14th Ave: Permanently
Westbound Sandy traffic is permanently DIVERTED to Couch, to 12th, to Sandy. Detour to Burnside Bridge is Sandy to Couch. (Burnside / Couch Couplet Project)
N Weidler St – Broadway to Ross, lane closures: Now thru September 3
Sidewalk, track, and utility work are underway, followed by paving work. (Paving work is weather dependant.) Expect significant traffic congestion & delays due to lane closures. (Portland Streetcar Loop Project)
Eastbound access to I-84 from Burnside Bridge
Access to I-84 from the Burnside Bridge is now Burnside St eastbound to Grand Ave northbound via a newly allowed left turn. (Burnside / Couch Couplet Project)
SE Grand Ave – Harrison to Mill, lane closures: August 27 – September 17
Sewer work is being performed, followed by water and paving work. (Paving work is weather dependent.) Expect congestion and delays. (Portland Streetcar Loop Project)
SE Grand Ave – Belmont to Pine, lane closures: Now thru September 10
Water work is being performed, followed by paving work. (Paving work is weather dependent.) Expect congestion and delays. (Portland Streetcar Loop Project)
NE MLK Blvd – Holladay to Davis, lane closures: Now thru September 10
Sewer work is being performed, followed by paving work. (Paving work is weather dependent.) Expect traffic congestion and delays. (Portland Streetcar Loop Project)
SE MLK Blvd – Ankeny to Morrison, lane closures: Now thru September 10
Sewer work is underway, followed by paving work. (Paving work is weather dependant.) Expect traffic congestion & delays. (Portland Streetcar Loop Project)
SE MLK Blvd – Main to Mill, *possible* lane closures, Now thru September 3
Sewer work is underway, followed by paving work. (Paving work is weather dependant.) Expect traffic congestion & delays. (Portland Streetcar Loop Project)
SE 10th Ave – at Oak, intersection closed: Now thru November 2010
The SE 10th and Oak Street Drop Shaft sewer crews are excavating the shaft. The intersection will be closed in all directions. Traffic will be detoured around the intersection. (Oak Basin Sewer Project)
SE 10th Ave – Pine to Stark, local access only: Now thru November 2010
For the SE 10th and Oak Street Drop Shaft project (see above item). Local access only. Expect traffic detours. (Oak Basin Sewer Project)
NE 13th Ave – Burnside to Couch, CLOSED: Permanently
This segment of 13th Ave is now CLOSED permanently as part of the street reconfiguration plan for the Burnside / Couch Couplet project. (Burnside / Couch Couplet Project)
NE 14th Ave – Burnside to Davis, ONE-WAY northbound: Permanently
This segment of 14th was once Two-Way traffic, but has changed to ONE-WAY northbound traffic permanently. (Burnside / Couch Couplet Project)
_______________________________________________________
The above information from Portland Bureau of Transportation’s “Keep Portland Moving” is expected traffic conditions for the coming week that was prepared on August 19, 2010, and is based on currently known construction traffic control plans. It is subject to change due to weather and/or other unforeseeable conditions.
Prepared by Will Stevens, Inner Eastside Keep Portland Moving, 503-823-2267.
The Portland Bureau of Transportation fully complies with Title VI of the Civil Rights Act of 1964 and related statutes and regulations in all programs and activities. For accommodations and additional information, contact the Title II and Title VI Coordinator at Room 1204, 1120 SW 5th Avenue, Portland, OR 97204 or by telephone at 503-823-2559, City TDD 503-823-6868.
Recent Comments